Road II/310 Žamberk-through road, 2nd phase | |
INVESTOR: Pardubice Region | |
| DESIGNER: STRADA v.o.s. Hradec Králové | |
| MAIN CONSTRUCTOR: ing.Aleš Kroupa | |
| REALIZATION PERIOD: 05/2005 - 11/2005 |
TOTAL COSTS: CZK 26,9 million (EUR 0,9) |
Construction of the new part of the through road II/310 with the length of 205 m and modification of the existing road I/11 in the entrance point to this road. A new direct intersection with a turning lane was built here. The construction of supporting and retaining walls that run along the whole road and relocation of underground services were components of this construction. | |