Long-welded rail structure in the railway junction Bohumín
INVESTOR:
TCHAS, spol. s r.o.
DESIGNER:
Chládek a Tintěra, Pardubice a.s.
PERSON IN CHARGE:
Jaroslav Lustig
REALIZATION PERIOD:
03/2005 - 10/2005
TOTAL COSTS:
CZK 5,4 million (EUR 0,18)
This construction is a part of the project “Optimalization of the railway junction Bohumín”. Work in the railway station on the even station rails involved welding about 750 welds of the rail shape S49, R65, UIC60 using technology SoWoS and long-welded rail structure in the length of 3500 m.