Long-welded rail structure in the railway station Třebovice v Čechách
INVESTOR:
Skanska ŽS a.s.
DESIGNER:
Chládek a Tintěra, Pardubice a.s.
PERSON IN CHARGE:
Jaroslav Lustig
REALIZATION PERIOD:
4.5.-24.6. 2004
TOTAL COSTS:
CZK 1,9 million (EUR 0,06)
This construction is a part of the project “Optimalization of the railway track Krasíkov – Česká Třebová”. Our company performed long-welded rails, rail replacement and rail welding. A long-welded rail was performed on 5 station rails and 10 switches. 271 welds were welded up in total.