Long-welded rail structure between Pardubice - Kostěnice | |
| INVESTOR: ŽS Brno | |
| DESIGNER: Chládek a Tintěra, silnice-železnice, Pardubice a.s. | |
| PERSON IN CHARGE: Josef Krčmář, Jaroslav Lustig | |
| REALIZATION PERIOD: 04/2001-11/2001 |
TOTAL COSTS: CZK 2,7 million (EUR 0,09) |
The construction is a part of the project “Modernization of the Pardubice – Uhersko railway track”. There was a long-welded rail performed on both rails and 633 welds were welded up in total. | |
Long-welded rail structure in the railway station Vraňany | |
| INVESTOR: ŽS Praha | |
| DESIGNER: Chládek a Tintěra, silnice-železnice, Pardubice a.s. | |
| PERSON IN CHARGE: Jaroslav Lustig | |
| REALIZATION PERIOD: 08/2001-11/2001 |
TOTAL COSTS: CZK 2,5 million (EUR 0,08) |
There was performed a long-welded rail on station rails and switches. 618 welds were welded up and 8 A-LIS were assembled. | |
Long-welded rail structure in the railway station Kunčice | |
| INVESTOR: ŽS Brno a.s. | |
| DESIGNER: Chládek a Tintěra, silnice-železnice, Pardubice a.s. | |
| PERSON IN CHARGE: Jaroslav Lustig | |
| REALIZATION PERIOD: 05/2001-06/2001 |
TOTAL COSTS: CZK 2,2 million (EUR 0,07) |
The construction is a part of the project „ČD, DDC, Improvement of the railway station Ostrava Kunčice, gridiron in Bartovice”. A long-welded rail was performed, 384 welds were welded up and 78 A-LIS were assembled. | |