Long-welded rail structure between Pardubice - Kostěnice
INVESTOR:
ŽS Brno
DESIGNER:
Chládek a Tintěra, silnice-železnice, Pardubice a.s.
PERSON IN CHARGE:
Josef Krčmář, Jaroslav Lustig
REALIZATION PERIOD:
04/2001-11/2001
TOTAL COSTS:
CZK 2,7 million (EUR 0,09)
The construction is a part of the project “Modernization of the Pardubice – Uhersko railway track”. There was a long-welded rail performed on both rails and 633 welds were welded up in total.





Long-welded rail structure in the railway station Vraňany
INVESTOR:
ŽS Praha
DESIGNER:
Chládek a Tintěra, silnice-železnice, Pardubice a.s.
PERSON IN CHARGE:
Jaroslav Lustig
REALIZATION PERIOD:
08/2001-11/2001
TOTAL COSTS:
CZK 2,5 million (EUR 0,08)
There was performed a long-welded rail on station rails and switches. 618 welds were welded up and 8 A-LIS were assembled.





Long-welded rail structure in the railway station Kunčice
INVESTOR:
ŽS Brno a.s.
DESIGNER:
Chládek a Tintěra, silnice-železnice, Pardubice a.s.
PERSON IN CHARGE:
Jaroslav Lustig
REALIZATION PERIOD:
05/2001-06/2001
TOTAL COSTS:
CZK 2,2 million (EUR 0,07)
The construction is a part of the project „ČD, DDC, Improvement of the railway station Ostrava Kunčice, gridiron in Bartovice”. A long-welded rail was performed, 384 welds were welded up and 78 A-LIS were assembled.