Track repair Čachnov - Skuteč
INVESTOR:
ČD a.s., SDC Pardubice
DESIGNER:
Chládek a Tintěra, Pardubice a.s.
MAIN CONSTRUCTOR:
Richard Tláskal
REALIZATION PERIOD:
8/2005
TOTAL COSTS:
CZK 7,7 million (EUR 256 667)

Complete change of the railway top, placing sleeper anchors, setting up a long welded rail and a crossing construction. The whole construction was realized in difficult slope (average slope 20%O) and direction ratio (arch of radius 200-260m) on the railway track between Žďárec u Skutče – Svitavy.