Repair of the track between Přelouč – Prachovice km 14,700 – km 15,220 and km 16,065 – km 17,240 | |
| INVESTOR: ČD a.s., SDC Pardubice | |
| DESIGNER: Chládek a Tintěra, Pardubice a.s. | |
| MAIN CONSTRUCTOR: Tomáš Kakrda | |
| REALIZATION PERIOD: 5/2004 – 6/2004 |
TOTAL COSTS: CZK 13,9 million (EUR 0,463 million) |
Reconstruction of the railway superstructure on the track Heřmanův Městec – Prachovice. In the whole section was built a railway superstructure of the shape of S49 on the concrete sleepers. Directive and vertical parameters were also treated.
The railway crossing on the road of the 3rd class leading to Práchovic was treated as well. As a suitable level railway crossing with regard to heavy traffic was selected a construction with rail protection and bituminous surface. The second crossing with minimum load was repaired directly in the station Kostelec. It was fixed by timber and treated by bitumen. In the whole section improvement of slopes and banks was carried out. Their slope was adjusted according to regulation for railway substructure ČD and they were rid off vegetation reaching passage section. | |
|
Range of work: Repair of railway superstructure in the whole partConstruction of a new crossing construction Slope treatment of trackbed | |